Macon, Georgia is getting a Georgia Power battery
Georgia Power builds four new battery storage facilities. One''s in Bibb County. Georgia Power hosted company and project leaders, as
Georgia Power announced today that construction is underway on 765-megawatts (MW) of new battery energy storage systems (BESS) strategically located across Georgia in Bibb, Lowndes, Floyd and Cherokee counties.
Georgia Power breaks ground at the McGrau Ford Battery Facility in Cherokee County on April 4, 2025. This 530-megawatt battery energy storage system will consist of two phases, approved in the 2022 Integrated Resource Plan (IRP) and 2023 IRP Update. Courtesy: Georgia Power.
As of this week, construction on those projects is officially underway. In total, 765 megawatts (MW) worth of new BESS will be strategically located across Georgia in Bibb, Lowndes, Floyd, and Cherokee counties.
An additional 1,000 MW of new battery energy storage is expected to be procured in the coming years through competitive bidding processes and a 13 MW demonstration project is in development at Fort Stewart Army Installation near Savannah, Georgia.
PDF version includes complete article with source references. Suitable for printing and offline reading.
Download detailed product specifications, case studies, and technical data for our off-grid PV containers and mobile energy storage solutions.
15 Innovation Drive
Johannesburg 2196, South Africa
+27 87 702 3126
Monday - Friday: 7:30 AM - 5:30 PM SAST